RAJOURI, Aug 26: District Development Commissioner Rajouri, Vikas Kundal today chaired a meeting of the concerned officers to review the physical and financial progress of the languishing projects of the PWD(R&B) sector.
Taking stock of the progress in Rajouri subdivision, the ExEn informed that out of 60 projects, the work on 41 projects is complete in all respects, while the work on 19 is under execution.
Similarly, while reviewing the progress in Nowshera Subdivision, it was apprised that the work on 23 projects out of 34 projects is complete and the 11 projects are at different phases of execution.
The DDC set 2 month deadline for completion of remaining 17 projects including 06 in Rajouri and 11 in Nowshera subdivision. He also directed the officers to expedite the progress and ensure that all the Languishing projects are completed well before the end of this financial year.
Detailed discussion on the physical and financial progress on CRF projects was also held in the meeting. The meeting also reviewed the status of work on Health buildings and college campuses.
Addressing the officers during the meeting, the DDC directed the officers to work with proper dedication to achieve development goals to cater the needs of the district with focus on creating tangible assets.
He also exhorted for mobilizing men and machinery for completing the works in stipulated time frame. He urged to ensure productive and fruitful utilisation of the available resources.
Discussing issues impeding execution of developmental works, the DDC stressed on working in close coordination so that the execution don’t get delayed on ground.