Excelsior Correspondent
JAMMU, Oct 13: Superintending Engineer, O&M Circle, Jammu JPDCL has informed that for hooking of 11KV HT AB cable on existing poles required for shifting of 33KV Janipur-Muthi Line under Languishing Project, the power supply to Pamposh Colony, Skaghal opposite, Government Quarter Janipur, Bhawani Nagar, Lakad Mandi, Indira Colony, Daily Excelsior lane, Nasib Nagar, Harderpur, BSNL Exchange, Ram Vihar, Patoli Chowk and its adjoining areas will remain affected on October 14 from 9.30 am to 2 pm.
Similarly, for HT tapping of New DT, the power supply to Gigrial, Sainth, Nikkian, Bhadwal, Garar and its adjoining areas will remain affected on October 14 from 9 am to 2 pm.
Meanwhile, Chief Engineer, (Distribution), JPDCL Jammu has informed that for shifting of the line from steel tubular poles to the newly erected tower, the shutdown of 132 KV Udhampur-Kishtwar transmission line is being observed.
During the shutdown, the power supply to District Kishtwar and part of District Doda will remain affected on October 14 from 9 am to 12 noon.