Excelsior Correspondent
JAMMU Dec 12: Chief Engineer (Distribution), JPDCL Jammu has informed that for reconditioning /oil leakage repairing of 10MVA Transformer, the power supply to Gangyal Industry will remain affected on December 13 from 10 am to 4 pm.
The Chief Engineer (Distribution), JPDCL Jammu has also informed that the power shutdown to Canal, Pouni Chack, Toph, Canal Road and adjoining areas scheduled to be availed on December 13 is cancelled.
Superintending Engineer (Distribution), JPDCL O&M Circle Kathua has informed that for interconnection of Switchyard equipments and control panels, the power supply to 66 KV MD Enterprises, Knit Fab, CTM, 66/11 KV R/Stn, Industry SICOP, Hatli Morh Ind. Area, SIDCO and SICOP Industry Area will remain affected on Dec 13 from 10 am to 11 am.
Similarly, the power supply to SICOP and SIDCO Industry Area will remain affected on December 13 from 10 am to 3 pm.
Likewise, for interconnection of Switchyard equipments and control panels by M/s Capital Electech, Pvt Ltd under PMDP Industrial Scheme, the power supply to Industrial Area, IID Centre, SICOP, Hatli-I, Hatli-II, Hatli Village, Maroli, Mehtabpur, Hote and adjoining areas will remain affected on December 13 from 11 am to 12 noon.