Dilapidated condition of Munsiff Court Mendhar

Excelsior Correspondent

JAMMU, Apr 10: In a PIL filed by Bar Association, Mendhar highlighting the dilapidated condition of the Munsiff Court Building, a Division Bench of Jammu & Kashmir and Ladakh High Court comprising Justice Tashi Rabstan and Justice Rajesh Sekhri has disposed of the PIL with a direction to the official respondents to expedite the matter for accord of administrative approval and release of funds for construction of building along with advocates’ chamber at the earliest.
When the PIL came-up for hearing, Division Bench observed, “in compliance to the directions passed by this court, High Court on its administrative side vide communication dated 30.12.2021 had forwarded DPR for construction of court complex (at Mendhar for an amount of Rs 1234.60 lakh to the Development Commissioner Works (DCW) for technical vetting”.
“However, the same was returned by the Development Commissioner Works, Public Works Department on 25.01.2022 with the request to clear certain shortcomings/observations. Accordingly, the High Court vide communication dated 25.01.2023 returned the rectified DPR for an amount of Rs 1158.48 lakh and requested the concerned for accord of administrative approval and release the funds for undertaking the work”, the DB said.
“The respondents have accordingly forwarded the rectified DPR again to the Development Commissioner Works (DCW) on 22.02.20232 for technical vetting and response of which is still awaited”, the DB said, adding “we deem it appropriate to dispose of the instant PIL with a direction to the official respondents to expedite the matter for accord of administrative approval and release of funds for construction of building of court of Munsiff Mendhar along with Advocates’ chamber at the earliest”.