Power shut down

Excelsior Correspondent
JAMMU, Jan 4: In order to carry out the installation of 3 KV CT/PT of 33/11 KV Sub-Station Transport Nagar (G-7 Line), the power supply to Transport Nagar and its adjoining areas will remain affected on January 6 from 9 am to 2 pm.
Similarly, to carry out installation of 11 KV Panels of 33/11 KV Sub Station Railway Complex, the power supply to Gandhi Nagar, Gole Market, Bikram Chowk, MES, University and its adjoining areas will remain affected on January 7 from 9 am to 3 pm.
Meanwhile, to carry out the installation of new 11 KV Bus Coupler and shifting of existing panels to new location of 33/11 KV Sub Station, Sarwai, the power supply to Civil Airport, Airforce Stn (Satwari), Military Hospital, Nai Basti, Satwari and its adjoining areas will remain affected on January 9 from 9 am to 3 pm.