Power shut down

Excelsior Correspondent
JAMMU, Mar 19: In order to carry out the development works by M/s IRCON under R-APDRP, the power supply to Industries of EPIP Kartholi Bari Brahmana fed from 11 KV feeder (K-02) emanating from 10 MVA EPIP R/Stn Kartholi, Bari Brahmana will remain shutdown on March 20 from 8 am to 5 pm.
Similarly, in order to carry out stringing work of ACSR Panther conductor on new 33 KV Babliana-Seora line (GG-3), the power supply to Seora, Gangyal, Babliana, Kunjwani, Jeevan Nagar and their adjoining areas emanating from 132/33KV Grid Station Gangyal will remain affected on March 20 from 10 am to 2 pm.
In order to carry out works to the 33KV Birpur Complex and Narbada emanating from 132/33 KV Grid Station BB-I, the power supply to Birpur Industry, Kannal, Seoda  Greater Kailash and Industries fed from 33 KV Narbada line will remain affected from 6 am to 11am on March 20.
Similarly, in order to carry out works to the 33KV, BB-II, New Kartholi and Ratnuchak Feeders, the power supply to Bari Brahmana Industry fed from BB-II feeder, Ratnu Chak, Birpur MES, Ratnuchak, Bari Brahmana Industry fed from New Kartholi feeder will remain affected from 10 am to 4 pm on March 20.
In order to carry out the development works by M/s IRCON Along the 33KV line feeding supply to 33/11 KV Sub-Station Transport Nagar (G-7 line) the power supply to Transport Nagar, Bhatindi, Malik Market and its adjoining areas will remain affected on March 20 from 10 am to 2 pm.
Meanwhile, the power supply to Gandhi Nagar, Rail Head, Bahu Plaza, Parts of Trikuta Nagar, RBI being fed from 33/11 KV JDA Complex (G-2 line) will remain affected on March 20 from 9 am to 4 pm.
Similarly, the power supply along 33/11 KV Sub-Station Nanak Nagar (33 KV G-3 feeder) affecting Nanak Nagar, part of Gandhi Nagar, part of Shastri Nagar, Hospital, PHE, will remain affected on March 22 from 9 am to 3 pm and on March 26 from 9 am to 4 pm.
Also, the shutdown of 132 KV S/C Gladni-Kalakote Transmission line has been allowed for March 20 and March 22 from 11 am to 5 pm in order to carry out the work for stringing of 33 KV Thathar-Bantalab section of new 33KV Barn-Bantalab transmission line being constructed under SDRF. Due to shutdown, the power supply to part of Akhnoor and Kalakote areas will be affected.