Excelsior Correspondent
JAMMU, Oct 25 : To carry out work of PCC pole erection and installation of LT AB cable by M/s IRCON International Ltd., the power supply to Prem Nagar, Christian Colony, Upper Gummat and Lower Gummat fed from DG-2 feeder will remain affected on November 1, 3, 5, 7 and 9 from 10 am to 2 pm.
The power supply will also remain affected to areas fed from DG-4 feeder on November 02, 04, 06, 08 and 10 from 10 am to 2 pm.
Similarly, to carry out works by the Executive Engineer, Transmission Line Maintt. Division-III, Udhampur, the shutdown of 220/132/33 KV Grid Station Udhampur along with 220 KV S/C Sarna-Udhampur Transmission Line is being observed.
During the shutdown, the power supply to districts of Udhampur, Kishtwar and Doda will remain affected on October 26 from 8 am to 12 noon.
Meanwhile, to carry out bifurcation work of JDA-5 feeder, the shutdown of 11 KV N-9 feeder emanating from Receiving Station Nanak Nagar is being observed.
During the shutdown, the power supply to Nanak Nagar and its adjoining will remain affected on October 26 from 8 am to 11 am.
Likewise, to carry out development works by M/s IRCON International Ltd under R-APDRP scheme, the shutdown of 11 KV SA-3 feeder is being observed.
During the shutdown, the power supply to Satwari and its adjoining areas will remain affected on October 26 from 8 am to 11 am.