Excelsior Correspondent
JAMMU, Dec 9: In order to carry out the work of dismantling old tower at location No. 104 and stringing of ACSR Panther Conductor on newly erected tower at location No. 104 of 132 KV Rajouri-Draba Transmission Line, the shutdown of 132 KV D/C Rajouri-Draba Transmission Line is being observed.
During the shutdown, the power supply to district Poonch will remain affected on December 10 from 10 am to 2 pm.
Meanwhile, to carry out works by M/s IRCON International Ltd under R-APDRP scheme, the shutdown of 11 KV feeders emanating from Receiving Station Nanak Nagar is being observed.
During the shutdown, the power supply to Muthi and its adjoining areas fed from 33 KV Janipur-Muthi feeder will remain affected on December 10 from 10 am to 12 noon.
Likewise, the power supply to areas fed from 33 KV Canal-Medical feeder will remain affected on December 10 and December 13 from 10 am to 2 pm.
The power supply to Krishna Nagar, Lajpat Nagar, Rajendra Nagar, Commerce College and adjoining areas fed from 11 KV C-18 feeder will remain affected on December 10 and December 13 from 10 am to 2 pm and to Shakti Nagar, PHE and adjoining areas fed from 11 KV C-19 feeder on December 10 and December 13 from 10 am to 2 pm.