JAMMU, Apr 21: In order to carry out stringing of conductor of 132 KV S/C Transmission line on D/C Towers from Grid Station Samba to RTSS Samba, the power supply to Samba town, Army, Mansar and Nud fed from 66 KV IGC Samba feeder emanating from 132/66 KV Grid Station Samba will remain affected on April 23 and 24 from 07 am to 04 pm.
Similarly, the power supply to Mansar and Nud fed from 11 KV Navodaya and 11 KV Mansar feeders will remain affected on April 22 and 23 from 07 am to 04 pm.
Meanwhile, the power supply to Channi Himmat, Channi Rama, Malik Market, Gurdawara, Chowadi, Sainik Colony, MNES, Sunjwah and its adjoining areas fed from 33 KV G-6 line emanating from 220/132/33 KV Grid Station Gladni will remain affected on April 23 from 10 am to 02 pm.
Likewise, the power supply to Karan Nagar, Gujjar Nagar, Panjtirthi, Jain Bazaar, Ustad Mohalla, Kachi Chawni, Julaka Mohalla, Hari Market, Balmiki Chowk, Boriawala Pump House and adjoining areas fed from 33 KV G-5, G-8 and G-4 lines emanating from Grid Station Gladni will remain affected on April 23 from 10 am to 02 pm.