Excelsior Correspondent
JAMMU, July 15: In order to carry out various development works by M/s IRCON International Ltd under R-APDRP scheme, the power supply to MES, Kalu Chak, Birpur, Data Talab, Madana and Ratnu Chak fed from 33 KV Ratnu Chak Feeder will remain affected on July 15, 17, 19, 21 and 25 from 07 am to 12 noon.
Similarly, the power supply to MES, Kalu Chak, Birpur, Data Talab, Madana, Ratnu Chak and Industrial area of Bari Brahamana fed from 33 KV Ratnu Chak and BB-2 feeders will remain affected on July 23 from 07 am to 12 noon.
Likewise, the power supply to industrial area, SIDCO Bari Brahmana fed from 11 KV BB-21 feeder will remain affected on July 17, 19 and 21 from 07 am to 09 am.
Meanwhile, the power supply to Muthi and adjoining areas fed from 11 KV T-4 and MU-05 feeders will remain affected on July 16, 18 and 20 from 07 am to 11 am.
Similarly, the power supply to Janipur Colony and adjoining areas fed from 11 KV J-3 feeder will remain affected onJuly 17, 19 and 21 from 07 am to 11 am.
Likewise, the power supply to Babliana and adjoining areas fed from BL-2, BL-5 and BL-3 feeders will remain affected on July 16, 17, 18 and 19 from 07 am to 11 am.
Meanwhile, the power supply to Sohajana, Mandal, Flian,Kandwal, Surya Chak, Ganeshpur and adjoining areas fed from 33 KV Canal to Chatha Line will remain affected on July 17 and 19 from 07 am to 12 noon.
Similarly, the power supply to Channi Himmat and adjoining areas fed from 11 KV CH-3 feeder will remain affected onJuly 17 and 19 from 07 am to 11 am.
Likewise, the power supply to Gandhi Nagar and adjoining areas fed from 11 KV JDA-1 feeder will remain affected onJuly 18 and 20 from 07 am to 11 am.
Meanwhile, the power supply to Sainik Colony and adjoining areas fed from 11 KV SC-2 and SC-1 feeder will remain affected on July 16, 17, 18, 19 and 21 from 06 am to 10 am.
Similarly, the power supply to Purani Mandi, Parade, Link Road, Shalimar, Pacca Danga, Bus Stand, Raghumnath Bazaar, Kanak Mandi, Partap Garh, PHE Parade, Telephone Exchange, Ranbir Market and adjoining areas fed from 33 KV Company Bagh-Parade Tap Line and 33/11 KV Transformer Bank-II at Receiving Station New Sectt will remain affected on July 16 from 6.30 am to 8.30 am.