Excelsior Correspondent
JAMMU, Sept 17: In order to carry out R-APDRP Part B works under cluster-II, the shutdown of 11 kV Feeders is being observed.
During the shutdown, the power supply to Shakti Nagar, Patel Nagar and adjoining areas will remain affected on September 18, 20and 22 from 10 am to 2 pm.
Similarly, the power supply to Shakti Nagar, Shiv Nagar and adjoining areas will remain affected on September 19 and 20 from 10 am to 2 pm.
Meanwhile, for replacement of worn out gaskets and washers of 1×10 MVA, 33/11 KV Power Transformer to stop leakage of oil, the shutdown of /11 KV Receiving Station Bantalab is being observed.
During the shutdown, the power supply to Bantalab, Radio Station, CRPF, Lakshmipuram Chinore, Exchange, AYUSH Hospital, Keran, Rajinder Nagar, and adjoining areas will remain affected on September 18 from 9 am to 12 noon.